Policy updateConcession Agreements2024 (Multiple Amendments)

HAM MCA revised: traffic risk insulation reconfirmed, TPC coverage rules tightened

Open NHAI

What changed

Several 2024 amendments to the Hybrid Annuity Model concession agreement clarified that the concessionaire bears zero traffic risk (annuity is paid regardless of toll collection), but tightened the definition of qualifying costs in TPC. Changes also introduced milestone-linked annuity adjustment triggers tied to NHAI's independent engineer certification process.

Action to take

Review the updated IE certification checklist before submitting your construction completion certificate. Uncertified milestones can delay annuity activation by one payment cycle (6 months).

Policy moved. CivilBolt updates your contract checklist.